Author: Marta Bajko (CERN)
-
IT String: from leak non-conformity observation to first commissioning phase
The IT String is in its operational phase, with many lessons already learnt during the tests so far. The path to this phase – including detection and resolution of a non-conformity, and cooldown – has provided valuable insights and fostered strong collaboration across teams. Leak non-conformity: detection to resolution Following the successful completion of most…
-
IT String – Completion of installation of major components and start of interconnection works
Davide Bozzini (CERN) Lucía Herrero Álvarez (CERN) Marta Bajko (CERN) Nicolás Heredia García (CERN) Samer Yammine (CERN) Sebastien Blanchard (CERN)The HL-LHC IT String installation is entering its final phase in the SM18 building at CERN. All major components are now in place, following a series of installation and validation activities executed by the end of 2024 and beginning of 2025. These tasks have been carried out on schedule, within scope and following extensive preparations…
-
IT String – results from SQXL commissioning and SCT, and preparations for installation of the cold powering system
Davide Bozzini (CERN) Marta Bajko (CERN) Nicolás Heredia García (CERN) Samer Yammine (CERN) Sebastien Blanchard (CERN)The operation of the IT String represents a significant milestone for the HL-LHC Project as it is where many state-of-the-art technologies developed for the HL-LHC will operate collectively for the first time. The installation and commissioning of this unique test stand have seen relevant achievements in recent months. Cryogenic system tests The IT String cryogenic…
-
Decision to delay the IT String test by one year and to limit the IT String test to one year operation
The HL-LHC magnets and cold powering systems are planned to be tested individually on dedicated test benches in the SM18 test facility at CERN or at the collaborators test facility (e.g. at Fermilab in the USA). The HL-LHC IT STRING will reproduce on the surface the configuration of the left side of Point 5 with…