Optimising HL-LHC activities for the LS3 schedule
The LS3 LHC schedule, including the HL-LHC activities, was presented at the LS3 Readiness Review on 11-13thSeptember 2024. Following this review, a significant update was announced: LS3 will commence in the LHC on 29thJune 2026. By then, the critical path duration for the LS3 LHC in-work schedule was 51.5 months. Thanks to an intense optimisation…
-
Long Shutdown 3 schedule and readiness review
The HL-LHC Project will culminate with the accomplishment of a very demanding installation phase during the Long Shutdown 3 (LS3). To assess the project’s readiness, a tracking process on the expected availability of equipment has been implemented. The careful follow-up of this installation schedule float plays an important role in the strategical decision-making process. It…